How the job runs

Eight steps, from the first conversation to the meter

The two that matter most to a buyer are the ones most installers leave off the diagram: the structural check before anything is drilled into the roof, and who handles the utility paperwork.

Illustrative image, not a Leo installation.

The installation journey

The eight steps

Nothing is ordered before the written proposal is agreed, and the utility side is ours to run.

  1. Consultation

    A conversation about what you are paying now, what you consume during daylight, and what the roof is. Most of what decides whether rooftop solar is worth it is in the first two.

  2. Site and roof survey

    The roof is inspected for structure, orientation, shading and access, along with the existing electrical supply and where the system would tie in. This is an engineering visit, not a sales visit.

  3. System design and written proposal

    Sizing, layout, the mounting arrangement, the electrical scheme and the price, in writing. Nothing is ordered before this is agreed.

  4. Approvals and net metering application

    The application to the distribution utility, and for residential systems the central subsidy application, are prepared and submitted. This is the step that most often decides how long the whole job takes.

  5. Structure and mounting

    Mounting structures fabricated and installed to the survey, fixed so that the roof's waterproofing survives the installation.

  6. Electrical installation

    Panels, inverter, DC and AC cabling, protection, earthing and lightning protection, and the tie in to your existing distribution.

  7. Testing and commissioning

    The installation is tested, then charged and commissioned with the utility's meter in place. You are shown what the system is doing and how to read it.

  8. Handover and maintenance

    Documentation handed over, with maintenance support afterwards through the same service engineers who cover the rest of the firm's work.

Step 04 in detail

Six steps with the utility, and who does each

The approvals are the step that most often decides how long the whole job takes. They run in the order the scheme requires.

  1. Application on the national portal and to the DISCOM

    Your electricity account, identity and ownership documents, and the bank account the assistance is paid into. Prepared by us, signed by you.

    Leo files
  2. Feasibility approval

    The utility checks the connection and the load and approves the size. We follow it up until it lands.

    The DISCOM
  3. Installation by a registered vendor

    Structure, panels, inverter, cabling, earthing and lightning protection, to the written proposal.

    Leo files
  4. Net-metering application and inspection request

    Filed with the utility once the system is installed, with the test reports.

    Leo files
  5. Inspection and the net meter

    The utility inspects the installation and installs the net meter. You are present; nothing to file.

    The DISCOM
  6. Commissioning report and the assistance

    The commissioning report goes on the portal; the assistance is released to the bank account you gave in step one.

    Leo files

Where to begin

Start at step 01, the consultation

Tell us what you are paying now and what the roof is. That is enough for us to say whether it is worth surveying.

Book a site visit