Andhra Pradesh Grid Interconnection

APCPDCL Net-Metering & Solar Interconnection Guide

Technical feasibility norms, voltage thresholds, bi-directional metering specifications, and utility liaison for rooftop solar under Central Power Distribution Company of Andhra Pradesh Limited.

State: Andhra PradeshHQ: Beside Government Polytechnic CollegeOfficial Solar Portal

Distribution Utility Profile

APCPDCL

Central Power Distribution Company of Andhra Pradesh Limited

Regulatory Commission
APERC (Andhra Pradesh Electricity Regulatory Commission)
Corporate Headquarters
Beside Government Polytechnic College, ITI Road, Vijayawada, Andhra Pradesh 520008
Official Consumer Portal
APCPDCL Corporate Portal

Operational Jurisdiction

5 Districts Covered

Grid-connected solar net-metering applications and MRT meter testing for all administrative revenue circles in these districts are processed through APCPDCL divisions:

KrishnaNTRGunturPalnaduBapatla

Key Urban Centers

Vijayawada, Guntur, Machilipatnam, Tenali, Narasaraopet, Amaravati

Technical Feasibility & Specs

Interconnection norms & thresholds

Statutory supply voltages, transformer capacity ceiling, and bi-directional meter specifications applicable for solar rooftop connections under APCPDCL.

01Voltage Limits

Supply Voltage Thresholds

Permissible interconnection supply levels based on total solar inverter AC output capacity:

LT Single-Phase
Up to 3 kW (single-phase 230V, extendable to 5 kW based on service line)
LT Three-Phase
Above 5 kW up to 56 kW (415V three-phase LT supply)
HT 11 kV Supply
Above 56 kW up to 1,000 kW (11 kV HT supply)
HT 33 kV Supply
Above 1,000 kW up to 5,000 kW (33 kV HT supply)

Supply conversion application can be bundled with solar feasibility filing.

02Feasibility Norms

Transformer & Load Caps

Statutory limits enforced by regulatory orders during technical scrutiny:

DTR Capacity Ceiling: 100%
Cumulative solar capacity on distribution transformers is permitted up to 100% of rated capacity under APERC Solar Rooftop Regulations.
Contracted Load Limit: Up to 100%
Consumers across residential, commercial, and institutional categories can install up to 100% of contracted load, subject to a 500 kWp net-metering ceiling.
Settlement Cycle
Monthly energy netting with credit carry forward across billing cycles
Banking Carry-Forward
Annual settlement period with surplus unutilized credits adjusted as per APERC tariff orders

Feasibility approval is valid for project execution and agreement signing.

03Meter Standards

Bi-Directional Net-Meter

Utility hardware specifications and calibration protocols:

Bi-Directional Net Meter
DLMS-compliant bidirectional four-quadrant static meter (Class 1.0 for LT, Class 0.5s for HT) complying with IS 13779 / IS 14697 and APERC technical guidelines
Solar Generation Meter
Unidirectional solar generation check meter installed on inverter AC output
Protocol Compliance
DLMS / COSEM protocol compliant with optical communication port
Testing Laboratory
APCPDCL Meter Relay Testing (MRT) Laboratory

Leo Solar handles procurement, lab testing delivery, and installation liaison.

Step-by-Step Workflow

4-Step Interconnection Timeline

From initial feasibility registration on the portal to grid synchronization and commissioning certificate release with APCPDCL.

0110 to 15 working days

Feasibility Application and Service Validation

Submission of online application on the APCPDCL solar portal or PM Surya Ghar portal using Service Connection Number (SCNO). ADE (Operation) evaluates local transformer capacity within 15 working days.

ResponsibilityApplicant and APCPDCL Operation Division
023 to 5 working days

Technical Feasibility Sanction and Agreement Execution

Receipt of technical clearance letter from APCPDCL followed by execution of the APERC standard Net Metering Interconnection Agreement with the Executive Engineer or ADE.

ResponsibilityApplicant and APCPDCL Divisional Engineer
037 to 14 working days

Plant Erection and MRT Meter Calibration

Turnkey installation of solar array, inverter, AC and DC protection boxes, and earthing pits. Submission of meters to APCPDCL MRT laboratory for calibration and official sealing.

ResponsibilityLeo Solar and APCPDCL MRT Division
045 to 7 working days

Site Inspection, Net Meter Synchronization, and Commissioning

Physical inspection by APCPDCL ADE (Operation), execution of anti-islanding functional test, installation of sealed bi-directional net meter and generation meter, and release of Commissioning Certificate.

ResponsibilityAPCPDCL ADE (Operation) and Leo Solar

Regulatory & Technical Guidance

Frequently asked questions for APCPDCL

Clear answers to common questions regarding distribution transformer headroom, billing adjustment, meter testing, and safety norms.

What are the sanctioned load rules for commercial consumers in APCPDCL?

Commercial consumers under APCPDCL in Vijayawada and Guntur can install solar capacity up to 100% of their contracted load, up to a maximum of 500 kWp under net-metering.

How does APCPDCL evaluate transformer feasibility in dense urban areas like Vijayawada?

APCPDCL assesses local transformer loading and cumulative solar connections against the APERC 100% rated capacity ceiling. If headroom is available, feasibility is approved within 15 working days.

What are the dual meter requirements under APCPDCL?

APCPDCL requires a bi-directional net meter at the grid interface point to measure import/export, and a separate generation meter at the inverter output to record total solar generation.

Can consumers upgrade from single-phase to three-phase for solar net-metering?

Yes. If your planned solar capacity exceeds 3 kW or 5 kW, you can apply for a service category conversion from single-phase to three-phase supply with APCPDCL.

How are solar export credits accounted for in APCPDCL billing?

Exported units are netted against imported units in each billing cycle. Surplus export units are carried forward across billing cycles within the annual settlement period.

Full Liaison Included

Ready to connect solar to APCPDCL?

Leo Solar handles your roof survey, structural design, online portal registration, MRT laboratory testing, and physical bi-directional meter synchronization with Central Power Distribution Company of Andhra Pradesh Limited.

Calculate Solar Savings & SubsidyChat on WhatsApp for Feasibility

Direct consultation with our Telangana & Andhra Pradesh utility engineering team.