Andhra Pradesh Grid Interconnection

APSPDCL Net-Metering & Solar Interconnection Guide

Technical feasibility norms, voltage thresholds, bi-directional metering specifications, and utility liaison for rooftop solar under Southern Power Distribution Company of Andhra Pradesh Limited.

State: Andhra PradeshHQ: D.No:19-13-90/AOfficial Solar Portal

Distribution Utility Profile

APSPDCL

Southern Power Distribution Company of Andhra Pradesh Limited

Regulatory Commission
APERC (Andhra Pradesh Electricity Regulatory Commission)
Corporate Headquarters
D.No:19-13-90/A, Vidyut Bhavan, Kesavayanagunta, Tirupati, Andhra Pradesh 517501
Official Consumer Portal
APSPDCL Corporate and Solar Portal

Operational Jurisdiction

10 Districts Covered

Grid-connected solar net-metering applications and MRT meter testing for all administrative revenue circles in these districts are processed through APSPDCL divisions:

TirupatiChittoorSPSR NellorePrakasamKurnoolNandyalAnanthapuramuSri Sathya SaiYSR KadapaAnnamayya

Key Urban Centers

Tirupati, Nellore, Kurnool, Kadapa, Anantapur, Chittoor, Ongole, Hindupur

Technical Feasibility & Specs

Interconnection norms & thresholds

Statutory supply voltages, transformer capacity ceiling, and bi-directional meter specifications applicable for solar rooftop connections under APSPDCL.

01Voltage Limits

Supply Voltage Thresholds

Permissible interconnection supply levels based on total solar inverter AC output capacity:

LT Single-Phase
Up to 3 kW (single-phase 230V, extendable to 5 kW based on service line)
LT Three-Phase
Above 5 kW up to 56 kW (415V three-phase LT supply)
HT 11 kV Supply
Above 56 kW up to 1,000 kW (11 kV HT supply)
HT 33 kV Supply
Above 1,000 kW up to 5,000 kW (33 kV HT supply)

Supply conversion application can be bundled with solar feasibility filing.

02Feasibility Norms

Transformer & Load Caps

Statutory limits enforced by regulatory orders during technical scrutiny:

DTR Capacity Ceiling: 100%
Cumulative solar capacity on distribution transformers is permitted up to 100% of rated capacity under APERC Solar Rooftop Regulations.
Contracted Load Limit: Up to 100%
Consumers across residential, commercial, and agricultural/institutional categories can install up to 100% of contracted load, subject to a 500 kWp net-metering ceiling.
Settlement Cycle
Monthly energy netting with credit carry forward across billing cycles
Banking Carry-Forward
Annual settlement period with surplus unutilized credits adjusted as per APERC tariff orders

Feasibility approval is valid for project execution and agreement signing.

03Meter Standards

Bi-Directional Net-Meter

Utility hardware specifications and calibration protocols:

Bi-Directional Net Meter
DLMS-compliant bidirectional four-quadrant static meter (Class 1.0 for LT, Class 0.5s for HT) complying with IS 13779 / IS 14697 and APERC technical regulations
Solar Generation Meter
Unidirectional solar generation check meter installed on inverter AC output
Protocol Compliance
DLMS / COSEM protocol compliant with optical communication port
Testing Laboratory
APSPDCL Meter Relay Testing (MRT) Laboratory

Leo Solar handles procurement, lab testing delivery, and installation liaison.

Step-by-Step Workflow

4-Step Interconnection Timeline

From initial feasibility registration on the portal to grid synchronization and commissioning certificate release with APSPDCL.

0110 to 15 working days

Feasibility Application via Online Portal

Submission of online application on the APSPDCL Solar Portal or PM Surya Ghar National Portal using Service Connection Number (SCNO). ADE (Operation) conducts field feasibility study on transformer loading within 15 working days.

ResponsibilityApplicant and APSPDCL Operation Division
023 to 5 working days

Technical Feasibility Clearance and Agreement Execution

Receipt of feasibility sanction letter followed by execution of the APERC standard Net Metering Interconnection Agreement with the APSPDCL Divisional Engineer.

ResponsibilityApplicant and APSPDCL Divisional Engineer
037 to 14 working days

Plant Erection and MRT Laboratory Testing

Turnkey installation of solar array, inverter, earthing pits, and surge protection. Delivery of meters to APSPDCL MRT testing laboratory for calibration, accuracy check, and official sealing.

ResponsibilityLeo Solar and APSPDCL MRT Division
045 to 7 working days

Site Inspection, Net Meter Synchronization, and Commissioning

Physical inspection by APSPDCL ADE (Operation), execution of anti-islanding functional test, installation of sealed bi-directional meter and generation check meter, and release of formal Commissioning Certificate.

ResponsibilityAPSPDCL ADE (Operation) and Leo Solar

Regulatory & Technical Guidance

Frequently asked questions for APSPDCL

Clear answers to common questions regarding distribution transformer headroom, billing adjustment, meter testing, and safety norms.

Why do districts like Ananthapuramu and Kurnool under APSPDCL experience higher solar yields?

The Rayalaseema region features some of the highest solar irradiance levels in southern India, typically exceeding 5.5 kWh per square meter per day, leading to strong seasonal generation performance.

What is the transformer capacity limit under APSPDCL?

Under APERC guidelines, cumulative solar capacity is allowed up to 100% of the transformer rated capacity. APSPDCL provides online tracking of available transformer capacity.

What are the high-tension (HT) net-metering requirements in APSPDCL?

HT installations (above 56 kW) connect at 11 kV or 33 kV, require Class 0.5s CT/PT metering, CEIG (Chief Electrical Inspector to Government) safety clearance, and vacuum circuit breaker (VCB) protection.

How does energy banking operate under APSPDCL net-metering?

Net export credits are banked in energy units (kWh) and adjusted against future consumption within the settlement year, helping seasonal agricultural and commercial establishments balance variations.

Can housing societies and gated communities in Tirupati or Nellore apply for group net-metering?

Yes. Housing societies can install rooftop solar on common roofs connected to their common-services meter (lifts, water pumps, lighting) under APERC net-metering guidelines.

Full Liaison Included

Ready to connect solar to APSPDCL?

Leo Solar handles your roof survey, structural design, online portal registration, MRT laboratory testing, and physical bi-directional meter synchronization with Southern Power Distribution Company of Andhra Pradesh Limited.