Skip to content
Rooftop solar installation

Telangana Grid Interconnection

TGSPDCL Net-Metering & Solar Interconnection Guide

Technical feasibility norms, voltage thresholds, bi-directional metering specifications, and utility liaison for rooftop solar under Southern Power Distribution Company of Telangana Limited.

State: TelanganaHQ: Mint CompoundOfficial Solar Portal

Distribution Utility Profile

TGSPDCL

Southern Power Distribution Company of Telangana Limited

Regulatory Commission
TGERC (Telangana State Electricity Regulatory Commission)
Corporate Headquarters
Mint Compound, Hyderabad, Telangana 500063
Official Consumer Portal
TGSPDCL Consumer and Solar Portal

Operational Jurisdiction

15 Districts Covered

Grid-connected solar net-metering applications and MRT meter testing for all administrative revenue circles in these districts are processed through TGSPDCL divisions:

HyderabadRangareddyMedchal-MalkajgiriVikarabadSangareddyMedakSiddipetMahabubnagarWanaparthyNagarkurnoolJogulamba GadwalNarayanpetNalgondaSuryapetYadadri Bhuvanagiri

Key Urban Centers

Hyderabad, Secunderabad, Cyberabad, Nalgonda, Mahabubnagar, Siddipet, Sangareddy

Technical Feasibility & Specs

Interconnection norms & thresholds

Statutory supply voltages, transformer capacity ceiling, and bi-directional meter specifications applicable for solar rooftop connections under TGSPDCL.

01Voltage Limits

Supply Voltage Thresholds

Permissible interconnection supply levels based on total solar inverter AC output capacity:

LT Single-Phase
Up to 5 kW (230V single-phase LT supply)
LT Three-Phase
Above 5 kW up to 56 kW (415V three-phase LT supply)
HT 11 kV Supply
Above 56 kW up to 1,000 kW (11 kV HT supply)
HT 33 kV Supply
Above 1,000 kW up to 5,000 kW (33 kV HT supply)

Supply conversion application can be bundled with solar feasibility filing.

02Feasibility Norms

Transformer & Load Caps

Statutory limits enforced by regulatory orders during technical scrutiny:

DTR Capacity Ceiling: 50%
Cumulative solar generation capacity connected to any distribution transformer cannot exceed 50% of the transformer rated capacity under TSERC Regulation 6 of 2016.
Contracted Load Limit: Up to 100%
Residential consumers may install solar capacity up to 100% of sanctioned contracted load; commercial and industrial consumers are capped at 80% of sanctioned load.
Settlement Cycle
Monthly net billing adjustment against retail tariff slabs
Banking Carry-Forward
Surplus energy credits carry forward across monthly billing cycles within the annual settlement period defined by TGERC tariff orders

Feasibility approval is valid for project execution and agreement signing.

03Meter Standards

Bi-Directional Net-Meter

Utility hardware specifications and calibration protocols:

Bi-Directional Net Meter
DLMS-compliant four-quadrant static bi-directional energy meter (Class 1.0 for LT, Class 0.5s for HT) complying with IS 13779 / IS 14697 and CEA metering regulations
Solar Generation Meter
Unidirectional static check meter installed at the inverter AC output to measure gross solar generation
Protocol Compliance
DLMS / COSEM protocol compliant with optical communication port
Testing Laboratory
TGSPDCL Meter Relay Testing (MRT) Laboratory

Leo Solar handles procurement, lab testing delivery, and installation liaison.

Step-by-Step Workflow

4-Step Interconnection Timeline

From initial feasibility registration on the portal to grid synchronization and commissioning certificate release with TGSPDCL.

0110 to 15 working days

Feasibility Application and Service Validation

Online application filing on the TGSPDCL Solar Portal or PM Surya Ghar National Portal using Unique Service Connection Number (USCNO). Section Officer reviews local distribution transformer headroom.

ResponsibilityApplicant and TGSPDCL Operation Division
023 to 5 working days

Technical Feasibility Sanction and Agreement Execution

Issuance of formal technical feasibility clearance letter followed by signing of the standard bipartite Net Metering Interconnection Agreement with the TGSPDCL Divisional Engineer.

ResponsibilityApplicant and TGSPDCL Divisional Engineer
037 to 14 working days

Turnkey Installation and MRT Meter Calibration

Supply, mechanical erection, dual chemical earthing, and protection switchgear installation. Bi-directional and generation meters submitted to TGSPDCL MRT laboratory for calibration, testing, and official sealing.

ResponsibilityLeo Solar and TGSPDCL MRT Division
045 to 7 working days

Site Inspection, Net Meter Synchronization, and Commissioning

Field inspection by TGSPDCL ADE (Operation), functional testing of anti-islanding trip relay within two seconds, physical installation of sealed meters, and issuance of Joint Commissioning Certificate.

ResponsibilityTGSPDCL ADE (Operation) and Leo Solar

Regulatory & Technical Guidance

Frequently asked questions for TGSPDCL

Clear answers to common questions regarding distribution transformer headroom, billing adjustment, meter testing, and safety norms.

Can I install a solar plant larger than my TGSPDCL sanctioned load?

Under TGERC regulations, rooftop solar capacity is bounded by your sanctioned contracted load. Residential consumers can install up to 100% of sanctioned load, while commercial and industrial installations are capped at 80%. If you require a higher capacity, a load enhancement application must be processed with TGSPDCL prior to or alongside the solar feasibility application.

How does TGSPDCL evaluate local transformer (DTR) feasibility?

TGSPDCL monitors cumulative solar injection on each distribution transformer. Cumulative solar capacity cannot exceed 50% of the transformer rated capacity under TSERC Regulation 6 of 2016. If the transformer is saturated, the utility issues a feasibility review detailing whether a transformer upgrade or capacity reduction is required.

Why does TGSPDCL mandate two meters for a grid-connected solar system?

TGSPDCL requires a bi-directional net meter at the consumer service point to record energy imported from and exported to the grid, plus a dedicated solar generation meter at the inverter output. The generation meter logs gross solar generation for regulatory compliance and renewable energy accounting.

How does net energy settlement reflect on TGSPDCL electricity bills?

Exported solar units are subtracted from imported grid units in each monthly billing cycle. Net positive consumption is billed at applicable retail tariff slabs. If export exceeds import, surplus credit units are banked and carried forward to subsequent billing cycles within the settlement period defined by TGERC tariff orders.

What anti-islanding safety features does TGSPDCL mandate during grid outages?

Inverters must comply with IEC 62116 / IEEE 1547 anti-islanding standards. In the event of a grid power failure, the inverter must automatically disconnect within two seconds to prevent back-feeding into de-energized distribution lines, ensuring the safety of utility maintenance staff.

Full Liaison Included

Ready to connect solar to TGSPDCL?

Leo Solar handles your roof survey, structural design, online portal registration, MRT laboratory testing, and physical bi-directional meter synchronization with Southern Power Distribution Company of Telangana Limited.

Calculate Solar Savings & SubsidyChat on WhatsApp for Feasibility

Direct consultation with our Telangana & Andhra Pradesh utility engineering team.